As of 17th of May 2023:
- Full Mine Mining Proposal approved by DMIRS.
- Drill and blast of first 5m bench completed.
- BML Ventures Pty Ltd to be fully mobilised with all mining activities operational by end of this week.
- Contractor to commence haulage to Greenfields mill at Coolgardie in late May.
- First gold pour expected early July.
- Cashflow to be generated for Auric commencing September/October 2023.
- Project duration May- September 23
- Cost per ounce $2042
- 48% ROI